Big Sur · 2008 to present
Esalen Institute Long-Term Development Plan
Monterey County approved the Esalen Institute’s Long-Term Development Plan in 2003 with conditions that protect Smith’s blue butterfly habitat, willow riparian forest, and other sensitive resources. Those conditions stay in force as the Institute builds, so each new project has to be checked against them. Toyon Consultants has supported the Institute’s long-term development plans across several projects and permitting issues.
Mitigation monitoring · NEPA compliance · CDFW 1600 permit · Biological assessment for a proposed water line replacement · Bridge replacement permit compliance and final report · Willow restoration planning · Biological letters for staff housing and a new well
What we did
- Monitored the plan’s restoration areas and reported to Monterey County.
- Guided the replacement of the Hot Springs Creek footbridge under a California Department of Fish and Wildlife streambed alteration agreement.
- Wrote biological letters for a water line reconstruction in 2010, staff housing in 2018, and a new well in 2025.
What we found
- The new bridge disturbed 1,145 square feet in all, none of it in the creek channel or the 100-year floodplain, and no listed species were harmed.
- The 2018 staff housing site is fill, covered mostly in non-native plants, so no added mitigation was needed.
- The 2025 well site is heavily disturbed with no sensitive habitat. Monarch butterflies could use the blue gum trees nearby.
Work included
- Mitigation monitoring
- NEPA compliance
- CDFW 1600 permit
- Biological assessment for a proposed water line replacement
- Bridge replacement permit compliance and final report
- Willow restoration planning
- Biological letters for staff housing and a new well